After magnesium oxide refilling, hot-state testing can only be performed after sintering, cooling to room temperature, and equipment assembly, followed by 30 minutes of power-on operation. The entire process, starting from sintering, typically takes 4–6 hours.

Hot-State Testing Timeline and Conditions

Stage

Time

Key Requirements

Sintering and Holding

1–2 hours

Ensure sufficient recrystallization of grains at 800–1000℃

Natural Cooling in Furnace

1–2 hours

Cool with the furnace to <200℃ to prevent thermal stress cracking

Cooling to Room Temperature After Removal from Furnace

30–60 minutes

Ensure component temperature stabilizes at approximately 25℃

Installation and Cold-State Testing

30 minutes

Complete assembly and pass cold-state insulation resistance (≥500 MΩ) and withstand voltage tests

Power-On Operation

30 minutes

Apply rated power to bring the heating element to normal operating temperature

The hot-state test should complete the insulation resistance measurement within 2 seconds after power-off, with a standard of ≥200 MΩ, to verify the stability of insulation performance at high temperatures.

Precautions: A cold-state test must be performed to confirm there is no risk of short circuit or breakdown before powering on; During operation, monitor the current and temperature rise curves to ensure there are no abnormal fluctuations; The ambient humidity should be ≤30% to avoid surface leakage affecting the readings.

Starting operation without sufficient cooling may lead to uneven internal stress release, causing microcracks or premature failure.