Insulation resistance testing requires a 500VDC megohmmeter. The procedure involves five steps: power off, disconnect, connect, apply pressure, and read the value. Especially in the high-temperature and high-humidity environment of Wuhan, it is essential to ensure the sensor is powered off and pre-dryed before testing to avoid misjudgment.

 

1. Pre-test Preparation (Safety First)

System Power Off: Turn off the power to the temperature control system to prevent high voltage damage to the control module during testing.

Sensor Removal: Disconnect the connection cable from the main control board and remove the sensor body from its installation position.

Surface Cleaning: Wipe the connectors, housing, and signal cable terminals with anhydrous alcohol to remove stains and moisture.

Air Drying: Place in a dry, ventilated area for at least 30 minutes, or purge with nitrogen for 5 minutes to remove surface moisture.

 

2. Test Equipment and Wiring

Use a 500VDC megohmmeter: Do not use a multimeter or low-voltage tester; a dedicated insulation tester must be used.

Correct Wiring Method:

Positive (+): Connect to both ends of the sensor signal line (short-circuit thermocouple poles);

Negative (-): Connect to the sensor's metal casing or armor layer;

Ensure Good Contact: Ensure the clamps are securely tightened to prevent contact resistance from affecting the reading.

Closed-Loop Operation: Before testing, use the megohmmeter's self-test function to verify the equipment is functioning correctly and ensure data reliability.

 

3. Pressure Testing and Reading Recording

Steps

Operating Points

Acceptance Criteria

Pressure Start

Press the test button and apply 500VDC voltage

Maintain stable pressure for 1 minute.

Read Value

Observe the stable resistance value after 1 minute

>100MΩ is normal.

Repeat Test

Test the same sensor 3 times and take the average value

A difference <10% is considered reliable.

 

4. Result Judgment and Follow-up Processing

Test Results

Judgment Conclusion

Handling Recommendations

>100MΩ

Good insulation

Can continue to be used, recommended to retest quarterly.

50~80MΩ

Slight moisture warning

Perform drying treatment and retest.

<50MΩ

Clearly moisture-damaged

Immediately stop use, dry and retest.

<10MΩ

Severe moisture damage or breakdown

Must be replaced, do not repair or use.